UVA selected Martin Horn to be their construction manager on the 5 1/2 month fast-track renovations of their baseball stadium. Working closely with the owner and VMDO Architects, UVA’s baseball stadium was transformed into one of the premiere college baseball facilities in the country. Bringing Martin Horn to the team early in the process allowed us to procure long lead items while finalizing the design details. The project received the Virginia Society of the AIA’s Honor Award as well as the Central Virginia Chapter of the AIA’s Merit Award.

PROJECT START:  September 2001
PROJECT SIZE:
2,000 seats + suites
PROJECT DURATION:
6 months
CONTRACT VALUE: 
$4 million
CONTRACT TYPE:
Lump Sum
PROJECT MANAGER:
John D. (Jack)Horn
SUPERINTENDENT: 
Mike McNulty
ESTIMATOR: 
Jack M. Horn
OWNER:
University of Virginia
C
ONTACT:
C.A. (Sack) Johannesmeyer
ARCHITECT:
VMDO
CONTACT:
Joe Celentano

At Martin Horn, the health and safety of our partners, team members, and community always comes first. It is this belief that continues to guide our actions, as we navigate the quickly evolving Coronavirus (COVID-19) pandemic. Martin Horn is closely monitoring guidance from the Centers for Disease Control (CDC), World Health Organization (WHO), and other government (federal and local) entities in real-time to inform operational decisions that safeguard the well-being of our partners and team members, alike. 

 

Due to the rapidly evolving landscape of this pandemic, this policy is subject (and likely) to change. To see the most up-to-date version of this policy, see the link below.

Martin Horn COVID-19 Policy