Ting Pavilion
This unique music pavilion required a significant amount of poured-in-place concrete that would be visible to the public in the finished product. To control both quantity and schedule, Martin Horn chose to self-perform all the concrete work. The Pavilion was a highly visible project completed in a high-traffic area with limited access.
PROJECT START: March 2025
PROJECT SIZE: 3,500 seat outdoor amphitheater
PROJECT DURATION: 135 days
CONTRACT VALUE: $3,450,000
CONTRACT TYPE: Design Build
PROJECT MANAGER: John D. (Jack) Horn
ESTIMATOR: Jack M. Horn
SUPERINTENDENT: Tim Patronik
OWNER: Charlottesville Pavilion LLC
CONTACT: Coran Capshaw
ARCHITECT: FTL Design Engineering