St. Thomas Aquinas Catholic Church, Phase II
Martin Horn was involved in preparing early estimates and in providing feedback on construction and scheduling. We then served as general contractor during construction under a cost plus a fixed fee contract and fixed general conditions with a guaranteed maximum price contract. Martin Horn also self-performed all the concrete work on both this and the next addition, which included exposed, stained concrete slabs covering interior and exterior surfaces.
PROJECT START: September 2002
PROJECT SIZE: 32,234 SF
PROJECT DURATION: 15 months
CONTRACT VALUE: $3.9 million
CONTRACT TYPE: Negotiated Cost Plus
PROJECT MANAGER: Ted Horn
SUPERINTENDENT: Tom Keegan
ESTIMATOR: Doug Horn
OWNER: St. Thomas Aquinas Catholic Church
CONTACT: Mimi Gomez
ARCHITECT: Train & Partners
CONTACT: Tom Keogh