Jack M. Horn operated as the senior project manager on the press and president’s boxes, miscellaneous site work and drywall packages. Working with VMDO as the architect, Martin Horn was able to fully complete the stadium projects on time and within cost estimates.
PROJECT DURATION CONTRACT VALUE
Scoreboard May ’98 – Mar ’99 $948,466
Drywall Nov ’98 – Mar ’01 $2,771,501
Press/President’s Box Feb ’99 – Sept ’00 $2,871,871
Site Improvements Feb ’99 – Sept ’00 $1,712,806
Temporary Partitions July ’99 – Dec ’99 $107,931
Lower Seating April ’99 – May ’99 $112,045
PROJECT START: May 1998
PROJECT SIZE: 61,500 persons
CONTRACT VALUE: $8,524,620
CONTRACT TYPE: Lump Sum
PROJECT MANAGER: Jack M. Horn
SUPERINTENDENT: Jeff Sims
ESTIMATOR: Jack M. Horn
OWNER: University of Virginia
CONTACT: Richard Laurance
ARCHITECT: VMDO
CONTACT: Joe Celentano