Architect Allan Greenberg, one of the foremost classicists practicing in the U.S., designed the Newman Pavilion addition to the Miller Center for Public Affairs. The project included extensive millwork and high-end finishes.

PROJECT START:  November 1989
PROJECT SIZE:
20,920 SF
PROJECT DURATION:
13 months
CONTRACT VALUE: 
$1.8 million
CONTRACT TYPE:
Lump Sum
PROJECT MANAGER:
John D. (Jack) Horn
SUPERINTENDENT: 
Harold Shifflett
ESTIMATOR: 
Jack M. Horn
OWNER:
University of Virginia
C
ONTACT:
Richard Dickman (retired)
ARCHITECT:
 Allan Greenberg Architects
CONTACT:
Doug Taylor

 

At Martin Horn, the health and safety of our partners, team members, and community always comes first. It is this belief that continues to guide our actions, as we navigate the quickly evolving Coronavirus (COVID-19) pandemic. Martin Horn is closely monitoring guidance from the Centers for Disease Control (CDC), World Health Organization (WHO), and other government (federal and local) entities in real-time to inform operational decisions that safeguard the well-being of our partners and team members, alike. 

 

Due to the rapidly evolving landscape of this pandemic, this policy is subject (and likely) to change. To see the most up-to-date version of this policy, see the link below.

Martin Horn COVID-19 Policy