Martin Horn renovated an auditorium in one of the oldest sections of the Law School into two tiered lecture halls, five offices and a seminar room. The schedule was very aggressive as the renovation needed to be finished for January 2007 classes. The lecture halls have some interesting finishes, including woodwork for sound proofing and a special tiered ceiling that echoes the shape of the tiered desks.

PROJECT START:  May 2006
PROJECT SIZE: 
5,700 SF
PROJECT DURATION:
6 months
CONTRACT VALUE: 
$1,611,969
CONTRACT TYPE:
Negotiated Lump Sum
PROJECT MANAGER:
Javier Luevano
SUPERINTENDENT:  
Mike Marks
ESTIMATOR:
Doug Horn
OWNER:
University of Virginia
C
ONTACT:
Bill Bergen
ARCHITECT:
Train & Partners
CONTACT: 
Tom Keogh

At Martin Horn, the health and safety of our partners, team members, and community always comes first. It is this belief that continues to guide our actions, as we navigate the quickly evolving Coronavirus (COVID-19) pandemic. Martin Horn is closely monitoring guidance from the Centers for Disease Control (CDC), World Health Organization (WHO), and other government (federal and local) entities in real-time to inform operational decisions that safeguard the well-being of our partners and team members, alike. 

 

Due to the rapidly evolving landscape of this pandemic, this policy is subject (and likely) to change. To see the most up-to-date version of this policy, see the link below.

Martin Horn COVID-19 Policy