In order to have this facility ready for fall sports, Martin Horn ordered the pre-engineered building in advance of final drawings. Technical challenges included humidity control in the hot tub area, unusual load requirements, and attaching the new facility to the link between U Hall and the Cage/Honesty Hall.

PROJECT START:  November 2004
PROJECT SIZE: 
5,679 SF
PROJECT DURATION:
9 months
CONTRACT VALUE: 
$997,372
CONTRACT TYPE:
Design-Build
PROJECT MANAGER:
Rocky Moulton
SUPERINTENDENT:  
Everett Bradburn & Steve Wingfield
ESTIMATOR: 
Doug Horn
OWNER:
University of Virginia
C
ONTACT:
Elizabeth Lawson
ARCHITECT:
 Osteen Phillips
CONTACT: 
Michael Osteen