This project consisted of a 3,050 sq. ft. gas station and convenience store, as well as a 1,050 sq. ft. single bay automatic car wash. The site’s previous structures; a convenience store, gas station and car wash; were demolished to make way for the new 7-Eleven, fueling station, and car wash. This site also contains a Jiffy Lube, which had to remain in operation at all times while new site utilities were installed to both buildings.

PROJECT START:  December 2012
PROJECT DURATION: 
8 months
CONTRACT VALUE: 
$944,040
CONTRACT TYPE:
AIA
PROJECT MANAGER:
Robert Menasco
SUPERINTENDENT: 
James Hanson
ESTIMATOR:
Doug Horn
OWNER:
Tiger Fuel
C
ONTACT: Gordon Sutton
ARCHITECT: Goetz Design Group
CONTACT: 
Eric Goetz

 

At Martin Horn, the health and safety of our partners, team members, and community always comes first. It is this belief that continues to guide our actions, as we navigate the quickly evolving Coronavirus (COVID-19) pandemic. Martin Horn is closely monitoring guidance from the Centers for Disease Control (CDC), World Health Organization (WHO), and other government (federal and local) entities in real-time to inform operational decisions that safeguard the well-being of our partners and team members, alike. 

 

Due to the rapidly evolving landscape of this pandemic, this policy is subject (and likely) to change. To see the most up-to-date version of this policy, see the link below.

Martin Horn COVID-19 Policy