The Tiger Fuel renovation consisted of a 3,388 sf gas station/convenience store and a 1,200 sf single bay automatic car wash. The site currently has an existing gas station/convenience store and car wash in operation. The project had two distinct phases with phase one including the demolition of the existingcar wash and construction of the new car wash and new convenience store. Phase two included closing and demolishing the existing store and installing the new fuel storage tanks and dispensers, concrete islands, concrete pads and canopy. The different construction materials being utilized were; turndown slab-on-grade, brick veneer, structural steel, bar joist, metal deck, EPDM roof system, aluminum entrance/storefront, EIFS, copper cladding, copper gutters and downspouts, skylights, ceramic tile, FRP and typical MEP items.

PROJECT START:  April 2008
PROJECT SIZE:  
1,200 SF
PROJECT DURATION:
7 months
CONTRACT VALUE: 
$1,169,160
CONTRACT TYPE:
AIA Limited Scope –Stipulated Sum
PROJECT MANAGER:
Carter Robertson
SUPERINTENDENT: 
Pete Schaus
ESTIMATOR: 
Carter Robertson
OWNER:
Tiger Fuel Company
C
ONTACT:
Paul Sisk
ARCHITECT:
The Goetz Design Group
CONTACT:
Eric Goetz

At Martin Horn, the health and safety of our partners, team members, and community always comes first. It is this belief that continues to guide our actions, as we navigate the quickly evolving Coronavirus (COVID-19) pandemic. Martin Horn is closely monitoring guidance from the Centers for Disease Control (CDC), World Health Organization (WHO), and other government (federal and local) entities in real-time to inform operational decisions that safeguard the well-being of our partners and team members, alike. 

 

Due to the rapidly evolving landscape of this pandemic, this policy is subject (and likely) to change. To see the most up-to-date version of this policy, see the link below.

Martin Horn COVID-19 Policy