Martin Horn was involved in preparing early estimates and in providing feedback on construction and scheduling. We then served as general contractor during construction under a cost plus a fixed fee contract and fixed general conditions with a guaranteed maximum price contract. Martin Horn also self-performed all the concrete work on both this and the next addition, which included exposed, stained concrete slabs covering interior and exterior surfaces.

PROJECT START:  November 1994
PROJECT SIZE:
22,000 SF
PROJECT DURATION:
13 months
CONTRACT VALUE: 
$1,917,324
CONTRACT TYPE:
Lump Sum
PROJECT MANAGER:
Jack M. Horn
SUPERINTENDENT: 
Tom Keegan
ESTIMATOR: 
Jack M. Horn
OWNER:
St. Thomas Aquinas Catholic Church
C
ONTACT:
James Stultz
ARCHITECT:
VMDO
CONTACT:
Joe Celentano