UVA Scott Stadium

Jack M. Horn operated as the senior project manager on the press and president’s boxes, miscellaneous site work and drywall packages. Working with VMDO as the architect, Martin Horn was able to fully complete the stadium projects on time and within cost estimates.

PROJECT | DURATION |CONTRACT VALUE

Scoreboard | May ’98 – Mar ’99 | $948,466

Drywall | Nov ’98 – Mar ’01 | $2,771,501

Press/President’s Box | Feb ’99 – Sept ’00 | $2,871,871

Site Improvements | Feb ’99 – Sept ’00 | $1,712,806

Temporary Partitions | July ’99 – Dec ’99 | $107,931

Lower Seating | April ’99 – May ’99 | $112,045

PROJECT START:  May 1998

PROJECT SIZE: 61,500 persons

CONTRACT VALUE: $8,524,620

CONTRACT TYPE: Lump Sum

PROJECT MANAGER: Jack M. Horn

SUPERINTENDENT:  Jeff Sims

ESTIMATOR: Jack M. Horn

OWNER: University of Virginia

CONTACT: Richard Laurance

ARCHITECT: VMDO

CONTACT: Joe Celentano