This unique music pavilion required a significant amount of poured-in place concrete that would be visible to the public in the finished product. To control both quantity and schedule, Martin Horn chose to self-perform all the concrete work. The Pavilion was a highly visible project completed in a high-traffic area with limited access.

Project Size: 3,500 seat outdoor amphitheater
Project Start: March 15, 2005
Project Duration: 135 days

Original Contract: $4,400,000
Final GMP: $3,500,000
Final Contract Value: $3,450,000
Contract Type: Design Build

Project Manager: John D. (Jack) Horn
Superintendent: Tim Patronik
Estimator: Jack M. Horn

Owner: Charlottesville Pavilion LLC